Well here we are about 3 weeks into the project. To remind you, my goal is to stay under $13,000 for this project. Here’s where we are:
Supplies: $3,143.19
There are some things that will get returned and I think conservatively we probably have another $1,500 left to purchase.
Hauling: $1,323.29
We’ve had 70 yards of debris hauled away! This price doesn’t include the dumpster from this weekend which I’m guessing is around $500-700.
Labor: $1,550.80
Includes Jaymie’s time and the concrete breaking. Probably have at least 1-2 more days of labor to pay for.
Misc. other: $787
Includes the electrical shutoff and demo permit.
Total: $6,504.28
Looking forward, we may come in close, but it’s going to be tight:
Gravel & dirt: $1,000
Hauling (done but not included in above): $700
Tool rental and additional labor: $600
Concrete dye: $100
Additional supplies: $1,500 (less any credit for returned supplies)
Plumbing & electrical: $1,500
Irrigation & lighting: $500
Landscape: $700+ this is sort of the whatever’s left over and if I want to spend a bit more section.
That would bring us right to $13,000! Hopefully we can stay on track and can bring this project in on-budget!